Berth Scour Protection for a 1.75 km Piled Jetty, Al Faw Grand Port, Iraq

A new deep-water container port needed 430,000 m³ of rock armour to protect its piled jetty, and local quarries could not readily supply it. Worse, rock has to be placed after piling but before the deck goes on, which put scour protection directly on the critical path. The alternative had to protect the same slope with a fraction of the material, and be installable at any point in the programme.

Al Faw Grand Port, 1.75km Piled Jetty
Project data

Location

Al Faw, Iraq

Client

Iraqi Ministry of Transportation

Designer

SENet

System

Insitu concrete mattress

Period

2022 – 2024

Results at a glance

26,500

Concrete placed

In place of 430,000 m³ of imported rock armour

94 %

Less material by volume

Sourced and batched locally, no quarrying or import

1.75 km

Piled jetty protected

Installed off the critical path, before, during or after deck construction

Contents

In brief

The constraints

Al Faw Grand Port is a new deep-water container port on Iraq’s southern coast, built to handle increased shipping traffic between Asia and Europe and to establish the country as a trade hub. The development involves extensive quay structures designed for large container vessels.

A critical component was berth scour: the erosion of sediment around the foundation piles caused by strong currents and wave action, which threatened the long-term stability of the marine structures.

Why rock armour did not work here

The original design specified traditional rock armour. Three problems followed from that choice.

Material sourcing and cost. Around 430,000 m³ of high-quality rock armour was required, in three layers totalling 3.6 m against the 220 mm of a mattress (Fig. 1). Suitable rock was limited in local quarries, so sourcing it meant substantial cost and the risk of delay.

Construction sequencing. Rock armour has to be placed after the piles are installed but before the deck is built. That put scour protection directly on the critical path, which is the recurring problem on piled revetments and jetties.

Environmental impact. Quarrying, transporting and placing that volume carried considerable carbon and ecological cost at both the source and the site.

FIG. 1 Section thickness compared. Three rock layers totalling 3.6 m against a single 220 mm mattress, and what each means for the jetty section.

The solution

Working with the designer SENet, Proserve proposed an insitu concrete mattress system in place of rock armour (Fig. 1).

The required material volume fell from 430,000 m³ of rock to 26,500 m³ of concrete. That reduced cost directly, and simplified logistics further: concrete could be sourced and batched locally, removing the quarrying and long-haul transport entirely.

It also changed the programme. Because the mattress can be installed before, during or after deck construction, scour protection came off the critical path, and deck works no longer had to wait for it.

Technically the fabric formed mattress makes a continuous concrete apron over the protection area, conforming to the seabed contours and sealing against the piles and the structure. With no open joints, there is no route for flow to reach and erode the bed material underneath.

FIG. 2 The two approaches under construction. Rock armour has to be placed between the piles before the deck goes on. The mattress can be installed before, during or after deck construction.

Design decisions

Two conditions drove the engineering: wave action on the upper slope, and expected settlement of the seabed beneath the jetty. Table 1 sets out each engineered feature and the condition it answers; Fig. 3 shows how the three mattress types are arranged down the slope, and Fig. 4 the open hole panel that takes the wave action.

Table 1 · Engineered features and the reason for each
FEATURE
VALUE
REASON
Wave-zone
thickness
0.35 m
Increased mass and resistance where wave action on the upper slope is most severe.
Permeability
holes
1.2 m centres
Let water move through the mattress, relieving uplift pressure from wave run-down.
Bedding stone
70 to 250 mm
Sized to prevent migration through the permeability holes while supporting the mattress contours.
FLEX webs
Every 1.2 m
Thin webs create segments that rotate slightly, so settlement cracks where intended rather than opening large cracks.
Settlement
allowance
Up to 290 mm
The seabed under the jetty was expected to settle after installation; the mattress had to follow it.
Settlement
collars
Steel, at each pile
Hold the mattress off the piles so it settles with the bed, avoiding stress concentrations at the pile interface.
Panel size
52.5 m × 7.5 m
Custom fabricated to give continuous coverage with the fewest joints across the protection area.
FIG. 3 Three mattress types down one slope. OHFLEX350 takes wave action on the upper slope over 14.9 m, FLEX200 absorbs settlement over 25.6 m, and CT220 runs 24.5 m across the berth.
FIG. 4 OHFLEX350. The relief holes let wave uplift pass through the slab instead of lifting it, and the segmented form follows the slope profile.

Constructability and installation

Installation was carried out by the marine contractor and their divers, with Proserve engineers supporting on site. Demonstration fillings were run at Al Faw before live work began (Fig. 5), so the dive team handled the fabric and watched it inflate before it mattered. Filling then ran alongside deck construction (Figs. 6 and 7), and the completed arrangement is shown in section at Fig. 8.

01

Submerge and position the fabric

Trained divers roll the geotextile formwork out along the seabed, following its contours and extending down the slope.

02

Secure to piles and structures

Restraining systems hold the form in position during filling and seal it against the piles, preventing under-bed erosion.

03

Fill with micro-concrete

Highly fluid micro-concrete is pumped into the submerged form from the surface, giving reliable filling over long pumping distances and a void-free slab.

04

Custom-fabricated panels

Panels of 52.5 m by 7.5 m give continuous coverage and structural continuity across the protection area.

05

Zip flap construction joints

The slope mattress connects to the berth mattress later, so it can be installed without impeding barge operations while keeping the slab continuous.

FIG. 5 Demonstration filling at Al Faw. The form laid out and fixed around the pile formers, then the same slope filled, so the dive team saw how the fabric behaves before it mattered.

Filling ran alongside deck construction rather than before it. Micro concrete was batched locally, delivered to the working platform and pumped down to the submerged form while precast beams, cages and deck pours continued around it, which is what taking scour protection off the critical path looks like on site.

FIG. 6 Filling during deck construction. Locally batched micro concrete pumped from the working platform, the delivery line floated out along the pile caps, with precast units and pile cages going in at the same time.
FIG. 7 The delivery line, floated. Buoyancy floats carry the hose out over the water and around each pile cap, so the pour reaches the panel without a barge.
FIG. 8 Typical section through the jetty. The apron runs continuously over the slope and berth, sealed against the piles.

Outcome

The zip flap construction joint is the detail that buys the programme freedom. Because the slope mattress can be connected to the berth mattress later, the slope can be protected without impeding barge operations, and the two parts still finish as one continuous slab. Combined with settlement collars at each pile, that means the apron can be placed before, during or after deck construction and still seal against every pile.

Removing scour protection from the critical path let deck construction and the other principal works proceed without waiting on it, which protected the programme against time overrun.

The reduction from 430,000 m³ of rock to 26,500 m³ of concrete produced the cost saving directly, and the simpler logistics of local batching against imported stone added to it. The same reduction cut the carbon associated with quarrying and haulage, and removed the ecological disturbance at the quarry source as well as at the site.

The completed apron gives the jetty continuous, sealed scour protection designed for the wave climate on the upper slope and able to follow the settlement expected beneath it. The same section logic applies to berth deepening where an existing structure sets the thickness available.

Also available
Credits

Who did what on this project

Client
Iraqi Ministry of Transportation

Owner of the Al Faw Grand Port development.

Designer
SENet

Adopted Proserve’s example design and integrated it into the overall project plans.

Scour protection engineering
Proserve

Engineering, custom design and on-site support through installation.

Formwork manufacture
HUESKER

Manufactured the geotextile formwork, drawing on over 160 years of weaving expertise.

FAQs

Questions engineers ask about this scheme

How thick is the concrete mattress at Al Faw?

0.35 m in the wave zone on the upper slope, where wave action is most severe, and 220 mm of constant thickness across the berth. The rock armour design it replaced needed three layers totalling 3.6 m.

Thickness is set by the design vessel and the wave climate, not by a standard product size. The section is engineered for each berth.

26,500 m³ of concrete in place of 430,000 m³ of imported rock armour, a reduction of more than 90 per cent by volume.

The saving is not only volume. The concrete was batched locally, so the quarrying, long-haul transport and the carbon and ecological cost that came with them were removed as well.

Yes. That is the main programme advantage over rock armour, which has to be placed after piling and before the deck goes on, putting scour protection directly on the critical path.

At Al Faw the apron could be placed before, during or after deck construction, so deck works never waited on it.

Settlement of up to 290 mm was expected beneath the jetty. FLEX webs every 1.2 m divide the slab into segments that rotate slightly, so the slab settles with the bed and cracks at the webs where intended, rather than opening large cracks.

Steel settlement collars at each pile hold the mattress off the pile so it can settle without concentrating stress at the interface.

Permeability holes at 1.2 m centres let water pass through the slab, relieving the uplift pressure generated by wave run-down instead of resisting it with mass alone.

Bedding stone graded 70 to 250 mm supports the mattress contours and is sized so it cannot migrate up through those holes.

Yes. It was presented as a peer-reviewed paper, Innovations in Berth Scour Protection for Piled Quays at Al Faw Grand Port, Iraq, by George Hawkswood at the 35th PIANC World Congress in 2024.

The paper and a PDF of this case study are both linked at the end of the article above.

Where next

Continue

THE TECHNOLOGY

Concrete mattress

How the form is filled, the six variants, and the published design basis behind the 0.35 m wave-zone section used here.

Read →
SAME PORT

Al Faw steel pile encasement

The other Proserve scheme on this quay: over 700 piles encased in 200 mm of concrete, one tide per jacket, no divers.

Read →
YOUR STRUCTURE

Piled revetments

Al Faw is a piled jetty. This is the same problem set out generally: protecting the slope beneath a deck, and keeping it off the critical path.

Read →
Work with our engineers

Designing scour protection for a piled jetty? Send us the berth geometry and vessel data.

Send us the berth geometry, the vessel classes and propeller arrangement, and the seabed conditions, and we will come back with an outline approach: apron extent, slope thickness, pile detail and where it sits in your programme. If rock armour is the better call on your project, we will say so.

What to send
No cost, and no obligation to proceed.