Encasing Over 700 Steel Piles, One Tide at a Time, Al Faw Grand Port

Over 700 steel piles on the first quay sit fully exposed between tidal cycles, in a highly aggressive marine environment. Cathodic protection was deemed ineffective above low tide. The original approach, precast concrete sleeves with annulus grouting, was labour intensive, diver dependent and poorly suited to the repetitive nature of the installation. The works needed a method that could be repeated over 700 times within the tidal windows.

Project data

Location

Al Faw Grand Port, Iraq

Client

Iraqi Ministry of Transportation

Designer

SENet

System

Marine Pile Encasement Concrete Fabric Formwork

Period

2022 – 2024

Results at a glance

700+

Piles encased

Vertical and raking steel piles on the first 1.75 km quay, all within the tidal limitations of the site.

200

mm encasement

Reinforced concrete cast insitu against the pile, over a prefabricated rebar cage.

1

Tide per jacket

Each jacket installed and filled inside a single low tide window, then stripped the next day and reused.

Contents

In brief

The constraints

Al Faw Grand Port is a flagship marine infrastructure development on Iraq’s southern Gulf coast, featuring one of the longest quay walls in the Middle East. The port’s first 1.75 km quay includes over 700 vertical and raking steel piles that are fully exposed between tidal cycles, in a highly aggressive marine environment subject to corrosion in the splash and tidal zones.

Conventional cathodic protection was deemed ineffective in this intertidal zone, because the piles spend so long exposed above low tide. A concrete encasement was selected instead as the most durable long-term protection, and the one able to meet the 100 year design life with minimal maintenance.

That decided the material but not the method. The original approach, precast concrete sleeves with annulus grouting, proved operationally inefficient on three counts: it was labour-intensive, it was diver-dependent, and it was poorly suited both to the tidal constraints and to the repetitive nature of an installation that had to happen over 700 times.

Table 1 · Encasement parameters
PARAMETER
VALUE
NOTE
Piles
over 700
Vertical and raking steel piles on the first 1.75 km quay.
Pile diameter
1.4 m
With 7 m of length in the exposed zone requiring encasement.
Encasement thickness
200 mm
Reinforced concrete, cast insitu against the pile.
Frame segments
3 stacked
Vertical segments, assembled onshore into one jacket unit.
Water:cement ratio
≈ 0.4
Achieved through bleed out of the fabric liner during filling.
Design life
100 years
With minimal maintenance requirements. The reason a concrete encasement was selected.
Fabric formwork
Grout-tight
Yet permeable, enabling water bleed and preventing grout washout.
Concrete
Site-batched
Achieving a dense, durable finish with reduced shrinkage.

The solution

Proserve developed the Lift-In Pile Encasement Jacket System: a modular, reusable solution combining factory-fabricated steel installation frames with grout-tight fabric formwork liners. The steel frame is the tool that is reused. The fabric liner is the form that casts the encasement.

Each pile jacket unit was assembled onshore in three stacked vertical frame segments, housing:

  • A fabric formwork liner, to cast the 200 mm thick reinforced concrete encasement.
  • A prefabricated rebar cage, to enhance structural integrity.
  • Quick-release ties and corner stiffeners, to maintain geometry during handling and casting.

Assembly onshore is what makes the difference. The unit arrives at the pile complete, with the liner, the cage and the stiffeners already inside the frame, so the overwater operation is a lift rather than a construction sequence. The same jacket system is applied to existing piles for structural remediation and protection, set out under marine pile repairs.

Constructability and installation

The cycle is four steps and it repeats, which is the whole point of it. Fabric formwork is used here in the same way it is used for grout bags and sock seals, as a form that adapts to what is already built rather than something the structure has to be adapted to suit.

01

Assemble onshore

Each pile jacket unit is built up on land from three stacked vertical frame segments, with the liner, the rebar cage and the stiffeners already inside it. Nothing is assembled over water.

02

Lift into position

The frame is lifted over the pile using mobile cranes. Because the unit is complete when it arrives, positioning is a crane operation rather than a construction operation.

03

Fill on the low tide

Concrete is tremie-pumped into the liner from the surface during the low tide window. The fabric is grout-tight yet permeable, so water bleed escapes naturally through it while grout washout is prevented, resulting in a low water:cement ratio of about 0.4 and a dense concrete finish.

04

Strip and reuse the next day

The steel frame is stripped the following day and moved to the next pile. The liner stays with the concrete. That reuse is what turns a one-off method into a production line.

One number is worth pausing on. The water:cement ratio here came out at approximately 0.4, below the figure given as typical for fabric formed concrete generally. It is the bleed that does it: water escapes through the liner during filling, and the concrete left behind is denser than what was pumped in. On a structure specified for 100 years in a chloride environment, that matters.

The other consequence is throughput. Because the jacket is installed and filled within a single tide and the frame is back in service the next morning, daily production is limited only by how many frames are on site. That is a scheduling problem rather than a marine operations problem, which is a much easier thing for a contractor to solve.

FIG. 1 Grouted pile jacket. The 200 mm reinforced encasement, cast insitu against the pile. The steel frame is stripped the next day and reused.

Outcome

The Lift-In Jacket System delivered a durable, buildable solution under difficult site constraints. The system minimised time-critical overwater working, significantly increased productivity, and removed the need for high-risk diver activity altogether. Key outcomes:

  • Efficient concrete encasement of over 700 piles within the tidal limitations of the site.
  • Reuse of formwork across the full installation, maximising resource efficiency.
  • Reduced marine risk by eliminating diver-based grouting.
  • Uniform, dense encasement with high resistance to corrosion and chloride ingress.
  • Enhanced programme certainty and minimised disruption to the parallel quay works.

This was not the only Proserve system at Al Faw. The berth scour protection to the same 1.75 km jetty is a separate scheme, and is covered in the Al Faw berth scour protection case study.

Wider use

Beyond new-build works like Al Faw, Proserve pile jacket systems are applied extensively in structural remediation and protection schemes worldwide:

  • Corrosion protection. Particularly suited to tidal and splash zone exposure, where sacrificial anodes or cathodic systems are ineffective.
  • Structural repair. Restores and improves the capacity of degraded piles through cast-in-place reinforcement.
  • Material compatibility. Applicable to steel, concrete and timber piles, in both tidal and submerged conditions.
  • Constrained access. Modular lift-in designs allow retrofitting under existing structures or in confined working zones.

The constrained access case is worth drawing out. Because the lift-in design is modular, it allows retrofitting under existing structures or in confined working zones, which is where conventional formwork runs out of room.

Also available
Credits

Who did what on this project

Client
Iraqi Ministry of Transportation

Owner of the Al Faw Grand Port development.

System developer
Proserve

Developed the Lift-In Pile Encasement Jacket System: factory-fabricated steel installation frames and grout-tight fabric formwork liners.

Where next

Continue

THE TECHNOLOGY

Fabric formed concrete

The method behind the liner: why a porous, grout-tight fabric gives denser concrete than a sealed shutter.

Read →
YOUR STRUCTURE

Marine pile repairs

The same jacket system applied to existing piles: corrosion protection and structural repair.

Read →
Work with our engineers

Piles corroding in the splash zone? Send us the pile and the tide.

Send us the pile type and diameter, the length needing encasement, and your tidal window, and we will come back with an outline: jacket configuration, encasement thickness, and how many frames the programme would need. New build or remedial, the system is the same.

What to send
No cost, and no obligation to proceed.