Berth Scour Protection for a Piled RORO Ferry Berth, Dunkirk, France

A new Dover-route berth taking twin-propeller ferries up to every 45 minutes, on a bed of fine sand. The protection had to go in beneath a completed piled deck, 50 m from a live ferry lane, and keep working as the bed around it dropped.

RORO 6 Ferry Berthing Port of Dunkirk
Project data

Location

Dunkirk Ferry Terminal, France

Client

Port of Dunkerque (GPMD)

Designer

Eiffage Génie Civil

System

Concrete mattress, hinged edge

Period

2023

Results at a glance

6,100

Concrete placed

In place of 9,000 to 12,000 t of rock armour

72 mattresses

Placed in 15 weeks

Finished a week ahead of programme, ferry service uninterrupted

50 M

From a live ferry lane

Installed beneath the completed deck with conventional plant

Contents

In brief

The constraints

RORO6 was built at Dunkirk Ferry Terminal to take increased traffic on the Dover route. It is the operating pattern of the berth, not any single event, that sets the scour problem.

Table 1 · Constraints on the protection
CONSTRAINT
VALUE
CONSEQUENCE
Berthing
frequency
Up to every 45 min
Cyclic loading with no quiet period for the bed to recover between arrivals, so the protection has to take it over the full design life.
Propulsion
Powerful twin
propellers
Extreme wash concentrated on the same area of bed each time, and no loose material can be left where a propeller could reach it.
Bed material
Fine sand
Highly erodible, so the apron has to stay in contact with a bed that will keep dropping.
Structure
Piled deck, already
complete
Placed and filled in the restricted space beneath a finished deck, with no cranage over it.
Proximity to
operations
50 m from a live ferry
lane
No disruption to ferry service, and no maintenance dredging burden left behind.
Available trench
depth
4 m
Sets how much scour the edge detail can follow before intervention.
Concrete Mattress Protection Area Dunkirk
FIG. 1 The protection area and the jetty to be constructed, inside the operating ferry terminal.

The solution

An insitu concrete mattress answers every line of that table. It gives a continuous protective layer around the piles and the berth structure, and it goes in as flexible rolled formwork that can be positioned, restrained and pump-filled in the restricted space beneath a completed deck.

Incomat formwork holds its dimensions as it fills, which is what made mattresses up to 55 m long placeable and fillable to thickness on variable gradients under the deck.

Port of Dunkirk Cross Section
FIG. 2 Cross section. The apron runs beneath the deck and out to the toe trench, where the hinged edge is embedded.

Hinged edge design

The hinged edge lets the mattress flex and settle gradually as scour develops beneath it. Rather than resisting the natural tendency of the seabed to erode, the hinged edge accommodates it, so the apron stays in contact with the bed and keeps protecting it even as local levels drop.

The trench is 4 m deep, enough for embedment and to take the early scour. Beyond that depth the design allows targeted addition in defined locations rather than protection sized for the worst case from the outset.

That removes the undercutting and toe failure that rigid or shallow-anchored protection is prone to, and it installs faster, with no complex shaping or deep backfill.

Concrete Mattress Hinged Edge
FIG. 3 CGI of the hinged edge. Not site photography: each edge unit drops independently into the scour hole beneath it, so the apron follows the bed instead of being undercut.

Pile seals and sliding restraint

Sealing around the piles was essential to stop vertical scour propagating down around each pile shaft, which is a vulnerability in many traditional scour protection systems and a recurring problem on piled revetments and jetties. The mattress incorporated tight pile seals, using tailored collars and infill fabric to wrap around the piles and tie back into the main mattress body.

Those seals prevent water jetting down the pile line, which would otherwise initiate focused scour holes; maintain the integrity of the apron so it stays continuous at every pile penetration; and reduce prop-wash interaction at the pile–mattress interface, which could otherwise lead to early failure. They were installed with close diver supervision and filled as part of the main pour sequence, giving both visual inspection and structural integrity during placement.

Concrete Mattress Pile Seal
FIG. 4 A sand-tight pile seal. Tailored collars and infill fabric wrap the pile and tie back into the apron, so flow cannot jet down the pile line and start a scour hole there.

The central compartment of each mattress provides sliding restraint, preventing longitudinal movement in the deep toe trench. That mattered here because of the sloping profile and the potential for the fabric to shift under hydraulic loads before the concrete cured. The general principles are set out in our article on preventing under-scour from vessel action. Filling that internal restraint zone first anchored the mattress before the hinged edge and upper fills were completed.

Constructability and installation

Installation was carried out by Eiffage Génie Civil, just 50 m from an active ferry lane, with no disruption to service. The team ran shore-based training and dry runs to refine techniques and mix design before live placement, and the mattress works finished a week ahead of programme.

01

Ballast the empty mattress

Divers carefully ballasted each empty mattress before filling, so it held its position on the bed.

02

Fill the sliding restraint first

Compartment 1, the central sliding restraint, is filled first, anchoring the mattress in the deep toe trench against longitudinal movement.

03

Then the hinged edge compartments

Compartment 2, the hinged edge, follows for stability before the upper fills go in.

04

Always start at the lowest point

Filling begins at the lowest point of each section, so concrete distributes evenly up the gradient.

05

Pour with the pile seals in sequence

Pile seals were filled as part of the main pour under close diver supervision, giving both visual inspection and structural continuity at each penetration.

Port of Dunkirk Pier
FIG. 5 A Grouting from the already constructed pier. The apron was placed and filled beneath the completed piled deck.
Table 2 · Installation figures
ITEM
VALUE
NOTE
Total concrete
volume
~6,100 m³
An equivalent rock solution would have required 9,000 to 12,000 t of material.
Mattresses placed
72
Over 15 weeks, finishing one week ahead of programme.
Filling rate
100 m³/day
Standard construction hours, typically 10 to 12 hours a day.
Longest mattress
Up to 55 m
Filled on variable gradients under the deck structure.
Port of Dunkirk Ferry Berthing
FIG. 6 A Vessel unberthing, bow thrusters washing up the slope. This is the loading the apron sees up to every 45 minutes.

Outcome

The berth carries a continuous sealed apron designed for the loading it actually sees: twin-propeller wash up to every 45 minutes, on fine sand that had already proved it would move. Because the edge follows the bed rather than resisting it, early scour is absorbed instead of undercutting the toe.

The works were completed in 2023, one week ahead of programme, with no disruption to ferry service throughout. Rock armour remains available to the port authority as a later, targeted addition if scour eventually exceeds the trench depth, and only in isolated areas.

Why it suited this berth


Material efficiency
Full-bed protection at reduced thickness. An equivalent rock solution could require 9,000 to 12,000 t of material depending on placement density.
Construction simplicity
Installed with conventional plant and dive teams beneath the completed deck.
Reduced dredging
The trenched, hinged design pre-empts early scour, reducing ongoing dredging in the high-energy zone.
Propeller safety
Unlike loose rock, the mattress gives a stable surface with reduced risk of propeller strike or movement under jet wash.
Maintainability
The hinged edge supports targeted rock addition by the port authority if scour eventually exceeds trench depth, in isolated areas and long after construction.

Conclusion

RORO6 shows what berth scour protection by insitu concrete mattress can do in a high-frequency, high-scour environment. With tailored trenching, sliding restraint and a hinged edge, the solution delivers long-term protection under demanding operational conditions, with logistical, cost and maintenance advantages over traditional rock armour.

Construction of the scour protection works was completed in 2023, giving a resilient and future-proof berth to support continued growth of the Dunkirk–Dover ferry service.

Also available
Credits

Who did what on this project

Client
Port of Dunkerque (GPMD)

Owner of the ferry terminal and the new RORO6 berth.

Contractor
Eiffage Génie Civil

Carried out installation of the scour protection, 50 m from an active ferry lane.

Scour protection engineering
Proserve

Concrete mattress system, hinged edge and trench detail, pile seals and the filling sequence.

Where next

Continue

THE TECHNOLOGY

Concrete mattress

How the form is filled, the variants, and the hinged edge and trench detail that lets a thin apron follow a scouring bed.

Read →
YOUR STRUCTURE

Piled revetments

RORO6 is a piled deck over a slope. This is the same problem set out generally: protecting the bed beneath a deck against propeller wash.

Read →
Work with our engineers

Designing scour protection for a RORO berth? Send us the berth geometry and vessel data.

Send us the berth geometry, the vessel classes and propeller arrangement, and the berthing frequency, and we will come back with an outline approach: apron extent, toe trench depth and the edge detail. If rock armour is the better call on your berth, we will say so.

What to send
No cost, and no obligation to proceed.