Scour Protection Under an Existing Piled Deck, Port of Eilat

A 60 year old jetty being refurbished needed scour protection placed underneath a deck that was already there, on an undulating slope, through a dense and irregular forest of piles. Some of those piles were more than 400 mm out of tolerance at bed level. Nothing rigid was going to fit, and there was no way to make the slope fit the protection instead.

Diver roll out
Project data

Location

Port of Eilat, Israel

Client

Israel Ports Development and Assets Co. Ltd.

Designer

SENet

System

Insitu concrete mattress

Period

2020

Results at a glance

5

Panel designs

Distinct mattress panel designs, developed because the pile spacing was irregular and one repeat panel would not fit.

24 × 5

M per panel

Each panel fully filled on site, with zip connections along the top and bottom edges sealing it to its neighbour.

575

MM in the wave zone

Thickened for a 3 m design wave height at 6.5 s peak period, stepping to a 300 mm transition compartment and 220 mm for the rest of the slope.

Contents

In brief

The constraints

A jetty undergoing refurbishment at the Port of Eilat required scour protection under the already existing deck. Given the undulating slope and the high density of piles at irregular spacing, the geometry itself was the problem: there was no repeating module to design to, and no access from above to correct anything that did not fit.

Two tolerance figures set the scale of that. Slope levels could vary to +0.1 / −0.3 m, and in some locations piles had been driven over 400 mm out of tolerance at bed level. Any protection system had to absorb both without a redesign on site.

FIG. 1 The jetty as work started. Deck slabs broken out between the beams, pile caps and reinforcement exposed. This is the access the mattress had to be installed through.
Table 1 · Site constraints
CONSTRAINT
VALUE
CONSEQUENCE
Working position
Under an existing
deck
The jetty was being refurbished, not rebuilt, so the protection had to go in beneath a deck that was already there.
Bed profile
Undulating slope
No flat bed to work from, and no possibility of levelling one.
Piles
High density, irregular
spacing
A dense forest of piles at spacings that do not repeat, so a single standard panel could not be used.
Slope level
variation
+0.1 / −0.3 m
The level of the slope itself varied by that much across the works.
Pile position
tolerance
over 400 mm
In some locations piles had been driven more than 400 mm out of tolerance at bed level.
Wave climate
3 m at 6.5 s
Design wave height of 3 m with a peak period of 6.5 seconds in the wave zone.
FIG. 2 Before the works, under the deck. Rows of piles receding into the distance, marine growth on every one, and a slope of loose rubble falling away to the right. This is the site the mattress had to be laid on and sealed around: not a prepared bed, and not a repeating grid.
FIG. 3 The working area, under the deck. Light reaches the bed only through the gaps between deck panels, and the piles run away in every direction at irregular spacing. Every panel had to be carried in and positioned by hand between them.

The solution

A geotextile formed concrete mattress had the capabilities the site demanded. The geotextile casts concrete in underwater conditions, and the fabric itself is lightweight and negatively buoyant, which means a single diver can handle it and manoeuvre it into place underwater. That is the whole basis of working under a live deck: the component gets to position by hand, not by crane.

Insitu concrete mattress is the preferred method for scour protection in piled revetments because of its reliability where maintenance access is limited. Rock protection has real advantages, porosity and ease of repair on level beds among them, but it becomes significantly more costly and difficult to install on sloped, piled structures. Increased flow velocities and turbulence around piles on inclined surfaces can also compromise the stability of rock armour, which raises the risk of failure exactly where you can least get back to it.

Pile tolerance and pile seals

This is the part of the job that decided the design. A mattress only works if bed material cannot escape from under it, and on a piled structure every pile is a hole through the apron that has to be closed. At Eilat the piles were not where a drawing would put them: in places they had been driven more than 400 mm out of position at bed level, and the slope they stand in varied by +0.1 / −0.3 m.

For construction on complex undulating slopes, the mattress formwork and the pile seals have to be engineered with surplus material, so the protection conforms to the arrangement of piles and slopes it actually finds. The fabric form takes the tolerance in three ways.

  • Internal pile seals, for piles that fall inside a panel. A sealed fabric collar is built into the panel at the surveyed pile position and pumped tight around the pile.
  • Half pile seals, at panel edges. The seal is split between two adjoining panels so a pile can sit on a joint line without either panel being cut.
  • Internal pile zips, so a panel can be opened, passed around a pile and closed again underwater, rather than being threaded over the pile head.
  • Surplus fabric throughout, so the form conforms to the slope and the as-driven pile positions instead of requiring either to be corrected first.

Pile bolsters achieved a sand-tight seal first time, and because the seals were filled as part of the main pour sequence, sealing was not a separate operation after it.

FIG. 4 A filled pile seal, on the bed at Eilat. The bolster is pumped tight against the pile it actually found, fill tube still attached, and the mattress runs into it.

Constructability and installation

Proserve tailored the fabric formwork to the required dimensions. Because of the irregular pile spacing, five distinct mattress panel designs were developed. Each panel measured 24 m by 5 m and was fully filled on site. Zip connections along the top and bottom edges of each panel sealed it to its neighbour, so the formwork achieved continuous protection with interlocking concrete aprons rather than a set of separate slabs with joints between them.

Internal vertical ties were woven directly into the fabric and anchored between the top and bottom layers of the formwork. Those ties do three jobs at once:

  • Automatic thickness control. The system inherently maintains mattress thickness, which reduces the need for diver intervention to adjust or reposition the formwork.
  • Reduced concrete usage. Minimised surface undulations give a more consistent thickness, so less concrete is needed to meet the minimum scour protection requirement.
  • Improved hydrodynamic stability. A smoother concrete surface reduces the risk of uplift from water forces acting on the mattress.

The other half of the constructability problem is what happens where the mattress meets each pile. A key principle of insitu concrete mattress is sealing around the structure so that bed material cannot be lost from under the concrete apron. On a complex undulating slope, the formwork and the pile seals must be engineered with surplus material, so the protection can conform to whatever arrangement of piles and slope it actually finds.

Pile bolsters were used to achieve a sand-tight seal first time. Sealing around each pile also prevents scour propagating down and around it, which is a known vulnerability in many traditional scour protection systems. The seals:

  • They prevent water jetting down the pile line, which would otherwise initiate focussed scour holes.
  • They maintain the integrity of the apron, ensuring continuity even at pile penetrations.
  • They were installed with close diver supervision and filled as part of the main pour sequence, giving both visual inspection and structural integrity during placement.
FIG. 5 Filling from the deck. Deck panels were lifted out between the beams to give the pump line access down to the mattress below.

Thickness and porosity

Thickness was not uniform, and deliberately so. An increased thickness of 575 mm was used in the wave zone to manage a design wave height of 3 m with a peak period of 6.5 seconds. In that zone the mattress also carries open holes of 80 mm diameter at 1.4 m centres, which provide the porosity needed to resist uplift during wave rundown. A stone layer of larger diameter than the holes is laid under the mattress there, so the porosity does not become a route for bed material to escape.

Table 2 · Mattress thickness by zone
ZONE
THICKNESS
BASIS
Wave zone
575 mm
Thickened to manage the design wave. Open holes of 80 mm diameter at 1.4 m centres provide porosity and resist uplift during wave rundown.
Transition compartment
300 mm
A step down from the wave zone, added specifically to optimise concrete usage rather than carry the thick section further than it was needed.
Remainder of slope
220 mm
The additional thickness was not required outside the wave zone.
FIG. 6 The design section. Thickness steps from 575 mm in the wave zone to 300 mm and then 220 mm, over a 600 mm bedding layer of 19 to 50 mm stone that assists grading the slope to level and stops bed material escaping through the open holes.

The drawing also carries the bed preparation the seals depend on. Bed levels on the slope are held to ±0.1 m to ensure the pile seals fit, using a bedding layer of 19 to 50 mm stone, typically 600 mm thick and never less than 200 mm, to assist grading the slope to level. In the OH575 wave zone the mattress sits on that bedding stone layer, which is what stops bed material escaping through the 80 mm holes.

The transition compartment is the detail worth noting. Rather than carrying 575 mm further than the wave climate justified, or dropping straight to 220 mm, a 300 mm step was designed in to optimise concrete usage across the slope.

Edge protection

Underscour, meaning loss of bed material at the edges, can lead to progressive failure of a mattress. Embedment of the mattress edge is fundamental to preventing it, and particularly so where the edge detail is a failing one such as mattress blocks or rock armour.

A rock falling edge apron was used here, designed on four points:

  • The edge trench was deep enough to contain the rock armour and large enough that it would not be displaced by flow.
  • Without that deadweight, displaced rock armour may roll onto the mattress protection area and affect draft clearance for vessels.
  • When edge scour occurs, the rock armour should settle into the localised scour holes.
  • Should scour exceed the designed depth, additional rock armour can be added.
FIG. 7 The boundary, underwater. The filled mattress is dressed up to the existing structure so the joint between apron and wall is closed rather than left open to flow.

The design intent is that the edge is allowed to move. Rock settles into scour holes as they form and keeps the mattress edge buried, and if scour ever goes beyond the designed depth the remedy is simply more rock, not a return to the mattress itself.

Outcome

The refurbished jetty was given continuous scour protection beneath its existing deck without the slope being levelled, the piles being corrected, or the deck being disturbed. The five panel designs conformed to the pile arrangement as it was actually built, including the locations more than 400 mm out of tolerance, and the zip connections closed the panels into a single interlocking apron rather than a set of independent slabs.

Thickness was matched to the wave climate rather than applied uniformly, with the 300 mm transition compartment holding concrete volume down across the slope, and every pile penetration was sealed as part of the main pour rather than as a follow-up operation.

Also available
Credits

Who did what on this project

Client
Israel Ports Development and Assets Co. Ltd.

Owner of the Port of Eilat and the jetty refurbishment.

Formwork design and supply
Proserve

Five tailored mattress panel designs, pile seals and bolsters, thickness zoning and the filling method.

Where next

Continue

THE TECHNOLOGY

Concrete mattress

The six variants, how thickness is held by internal ties, and where open-hole porosity is used.

Read →
YOUR STRUCTURE

Piled revetments

Eilat is a piled revetment problem. This is the same problem set out generally, with the rock armour comparison.

Read →
Work with our engineers

Protecting under an existing deck? Send us the pile layout and the slope.

Send us the pile layout, the bed survey and your wave climate, and we will come back with an outline: how many panel designs the spacing needs, the thickness zones, and how the pile seals would be detailed. If rock suits your bed better, we will say so.

What to send
No cost, and no obligation to proceed.