Insitu Concrete Foundations for 48 Marine Bridge Piers,Nouvelle Route du Littoral, La Réunion

Forty-eight bridge piers standing in cyclone-exposed water off the coast of La Réunion, each one bearing directly on the rock beneath it. Pier head height sets the alignment of the precast deck above it, so every base had to reach full bearing the moment it landed and hold it, with no settlement and nothing to adjust afterwards.

Nouvelle route du littoral reunion
Project data

Location

La Réunion, Indian Ocean

Client

VINCI Construction

Designer

5.4 km offshore viaduct, 48 piers

System

Foundation Grout Bag System

Period

2016

Results at a glance

48 piers

Marine pier foundations

Every pier of the offshore viaduct, consistent and repeatable

17,000

Cumulative foundation area

Bearing interface formed insitu, free of voids and washout

3,500

Grout placed from the surface

Batched onboard and tremie-pumped, no diver placement

Contents

In brief

The constraints

The Nouvelle Route du Littoral replaces the cliff-hugging National Route 1 on La Réunion with an alignment carried out over the sea. The island’s coastal infrastructure has long been vulnerable to closure and damage from tropical cyclones, heavy wave action and seismic risk, which is the reason the road was moved offshore in the first place.

The route includes 5.4 km of elevated bridge built between 80 m and 300 m from the shoreline, which makes every pier a sea bridge foundation rather than a land one. The viaduct carries precast concrete deck segments on 48 marine piers, each founded on rock strata at seabed level. Table 1 sets out the conditions the foundation interface had to work within.

Table 1 · Constraints on the foundation interface
CONSTRAINT
VALUE
CONSEQUENCE
Distance offshore
80 to 300 m
The viaduct runs between 80 m and 300 m from the shoreline, worked from marine plant and a temporary construction trestle.
Pier base
diameter
20 m or 23 m
A large footprint to bring into full-area water contact in one operation, landed on a gravel working layer over rock outcrop.
Seabed variation
Up to 900 mm
Differential bed conditions the interface had to take up without additional underwater concrete levelling.
Bearing
requirement
Full area, immediate
No settlement and no post-installation adjustment, because pier head height sets deck alignment.
Diver access
Restricted
High-flow marine conditions meant the filling operation had to be controllable from the surface.
Environmental
loading
Cyclone, wave,
seismic
The interface sits where wave impact, current scour and seismic acceleration all act.
2017.01.03 Fléau 47 pose V3
FIG. 1 Bridge construction. Deck segments are placed onto the piers offshore, which is why pier head height and alignment had to be held by the foundation rather than corrected later.

The solution

Proserve was commissioned to supply an engineered insitu concrete foundation using its foundation grout bag system, pre-attached to the underside of each pier base. Six independent grout bag compartments were fitted beneath each unit in the casting yard, in factory-manufactured woven fabric that is grout-tight but water-permeable, then filled in place once the pier was landed.

The design team required a foundation interface that would ensure intimate contact between the precast pier base and the gravel bed or rock outcrop beneath it, accommodate irregularities in seabed elevation without additional underwater concrete levelling, eliminate long-term settlement so pier head height and alignment hold across the viaduct, enable fully surface-controlled installation and grouting to avoid diver activity in high-flow marine conditions, and provide structural durability in a zone subject to wave impact, current scour and potential seismic acceleration.

Grouted fabric formwork was engineered to deliver a tailor-formed concrete base insitu through remote-controlled grouting. The formwork was sized for differential seabed conditions of up to 900 mm, which meant the contractor did not need to lay fine-grained stone beyond what was required to enable a moulded concrete interface.

The precedent mattered on a project of this exposure. The same system had already been used beneath the caissons of the MOSE flood barrier in Venice and at the Second Severn Crossing, so the filling method and the vent control were proven before La Réunion adopted them.

DSCN0021
FIG. 2 Formwork pre-installed in the casting yard. The six compartments are fitted, folded and sheathed beneath the base before the unit ever goes to sea.

Constructability and installation

Everything that could be done dry was done dry. Each pier base, either 20 m or 23 m in diameter, was cast in a controlled yard environment, and the six compartments were attached beneath it during fabrication. Each compartment was then condensed and folded for transport using break ties and protective sheathing, connected to dedicated cast-in filler sleeves running up through the pier shaft to deck level, and fitted with perimeter vent sleeves carrying grout sensors for pressure monitoring and fill confirmation.

That arrangement is what removes the diver from the critical operation. The filler sleeves were cast in and run up through the pier shaft to deck level, and the perimeter vent sleeves carried the grout sensors, so filling was both delivered and monitored from the surface.

01

Cast and fit at the yard

Each pier base, 20 m or 23 m in diameter, was cast in a controlled yard. Six independent grout bag compartments were attached beneath the unit during fabrication, in grout-tight but water-permeable woven fabric.

02

Condense, fold and sheath

Each compartment was condensed and folded for transport beneath the pier using break ties and protective sheathing, connected to cast-in filler sleeves running up the pier shaft to deck level.

03

Position offshore

The piers were transported out and positioned by gantry crane working off the temporary construction trestle, landing onto a pre-prepared gravel working layer on rock outcrop.

04

Hold on jack legs

Four external jack legs gave temporary vertical and lateral stability until grouting was complete.

05

Grout and monitor

A high-flow sand:cement micro-concrete, batched onboard, was tremie-pumped through the prefixed filler sleeves. Each operation ran 12 to 16 hours, with bag inflation watched continuously on the surface control panel fed by the vent sensor array.

The order of filling mattered. Grouting followed a fixed three-stage sequence, designed to seat the base axially first and then work outward.

The grouting sequence
01

Begin with the central compartments, to ensure axial seating

02

Progress outward radially, to minimise potential lift or rotation

03

Halt automatically once full contact pressure is detected at each vent

POSITIONED FILLED
FIG. 3 The same pier before and after grouting. Positioned on its jack legs with the bags still folded, then filled to full contact between the base and the bed. Drag the handle to compare.

That controlled sequence allowed both macro tolerance, meaning bed undulation, and micro tolerance, meaning gravel layer thickness, to be compensated within the foundation footprint. Grouting took 12 to 16 hours per pier, with bag inflation monitored continuously on the surface control panel fed by the vent sensor array, and the four external jack legs holding the unit until the fill was complete.

FIG. 4 A grouted base offshore. The filled compartments are visible around the perimeter, bearing between the base and the gravel working layer on the rock outcrop.

Outcome

The system gave consistent, repeatable foundation construction across all 48 pier locations, despite highly variable sea conditions and difficult site access. It delivered a cumulative foundation area of over 17,000 m², approximately 3,500 m³ of grout placed entirely from the surface, fully monitored compartmental filling for every pier, and load-bearing interfaces free from voids, washout or settlement potential.

Eliminating the large-volume underwater concrete pours and the diver-placed levelling significantly reduced risk in the offshore work zone. The system also provided long-term stability, contributing to the accuracy of the bridge deck alignment and the durability of the structure in a high-energy marine environment.

NO WEB/NO APPS Exclusive. A viaduct column is being laid by the 'Zourite' jack up barge (octopus in creole language) at the construction site of the New Coastal Highway (Nouvelle Route du Litttoral), in La Reunion Island, France in October 2017. The new
FIG. 5 The next segment placed on top of the base. Once the foundation is grouted and confirmed, the pier carries the column and deck above it without further adjustment.

Why it suited this project

  • Adaptability to complex bed profiles
  • Surface-only installation, enabling rapid and safe execution with no divers in the filling operation
  • Controlled uplift and internal pressure, preventing rotation of the base during grouting
  • A high-performance contact interface, with no reliance on compaction or blinding layers
  • Seismic and hydrodynamic resilience, supporting the design intent in a cyclone-prone zone

The same combination applies to marine foundations generally: structures that need precise placement, reduced marine risk and engineered reliability from a foundation formed in place.

Also available
Credits

Who did what on this project

Client and contractor
VINCI Construction

Delivered the offshore viaduct section of the Nouvelle Route du Littoral.

Foundation system
Proserve

Engineered insitu foundation using grouted fabric formwork, pre-attached beneath each pier base, and the surface-controlled grouting method.

Where next

Continue

THE TECHNOLOGY

Foundation grout bag system

The system in general: compartmented bags, cast-in filler sleeves, vent sensors, and where surface-operated filling replaces diver work.

Read →
YOUR STRUCTURE

Sea bridge foundations

The NRL is an offshore viaduct on discrete pier bases. This is the same problem set out generally: founding bridge piers on the bed as found, offshore.

Read →
Work with our engineers

Founding bridge piers offshore? Send us the base geometry and bed survey.

Send us the pier base geometry, the bed survey and the alignment tolerance you have to hold, and we will come back with an outline approach: compartment layout, fill and vent arrangement, and the grouting sequence. If a conventional bedding layer is the better call on your project, we will say so.

What to send
No cost, and no obligation to proceed.