Berth Deepening Scour Protection for an Existing Quay Wall, Port of Szczecin, Poland

The port needed to take larger vessels, which meant dredging an existing berth around 2 m deeper without undermining a wall that was never designed for that depth. Every millimetre of protection thickness is depth the wall does not get back. The Luxemburg return wall was also identified as unstable and in need of reinforcement.

Port Szczecin Concrete Mattress
Project data

Location

Szczecin, Poland

Client

Port of Szczecin

Designer

Aarsleff

System

Concrete mattress

Period

2024

Results at a glance

11,000

Sealed apron installed

Concrete mattress over the dredged berth pocket

1.9 m

Extra depth achieved

Berth taken from −10.6 m to −12.5 m for larger vessels

71 panels

Custom-made offsite

Averaging 185 m², each filled with 41 m³ of concrete

Contents

In brief

The constraints

The objective at Szczecin was to increase the berth depth from −10.6 m to −12.5 m, adding around 2 m so larger vessels could dock, without compromising the stability of the quay wall. Installation of 11,000 m² of concrete mattress scour protection was carried out by contractor Aarsleff.

The berth pocket was dredged to its maximum depth. Extra measures, including ground anchors at selected locations, were put in place to maintain the structural integrity of the quay wall.

Table 1 · Constraints on the protection
CONSTRAINT
VALUE
CONSEQUENCE
Existing depth
−10.6 m
The berth as built, and the depth the wall was designed to retain.
Target depth
−12.5 m
Around 2 m deeper, to take larger vessels at the same berth.
Dredging
tolerance
100 mm
The pocket was dredged to its maximum depth to this tolerance, leaving no margin to absorb a thick apron.
Wall stability
Ground anchors
required
Extra measures at selected locations to maintain structural integrity during and after deepening.
Vessel action
Propeller action
A sealed layer is needed, because an unsealed one requires deadweight and therefore thickness.
FIG. 1 Cross section. A 200 mm apron takes the berth from −10.6 m to −12.5 m, closing with a 560 mm hinged edge block set in a trench at the outer edge.
Port of Szczecin, Poland - Concrete Mattress
FIG. 2 Concrete mattress protection area. The extent of the apron along the quay.

The solution

When deepening an existing quay wall, using the thinnest possible protection maximises the depth achievable with the wall you already have. That is the whole argument for a sealed system here.

The insitu concrete mattress creates an interlocking layer that gives sealed scour protection, distributing hydrodynamic forces evenly across the apron and producing a stable, thin protective layer. Rock armour and unsealed mattress systems, by contrast, need extra deadweight to counteract hydrodynamic forces from propeller action and to resist trapped flow pressure, and that added weight increases the thickness of protection required.

Table 2 sets out the panel and filling figures behind the installation.

Table 2 · Panel and production figures
ITEM
VALUE
NOTE
Protection area
11,000 m²
Total sealed apron over the dredged berth pocket.
Panels
71
Formwork custom-made offsite to the precise site dimensions.
Average panel area
185 m²
Mean panel size across the 11,000 m² apron.
Concrete per panel
41 m³
Pumped in from the quayside, divers moving the hose between filler points.
Expected daily
output
82 m³
Two panels a day, subject to working areas and dive teams available.
Filling time
About 6 hours
Per panel, continuous from the quayside.
Hinged edge blocks
4 t each
Tied into the apron, designed to drop independently at the trench edge.

Constructability and installation

The whole sequence runs off the quay. Formwork is made offsite, lowered in and unrolled on the dredged bed, and filled with concrete pumped from the quayside, with dive teams moving the hose between filler points.

01

Roll out on the seabed

The formwork, custom-made offsite to the precise site dimensions, is rolled out on the dredged bed along the quay. It is fabric formwork, so it takes the shape of the bed it lands on.

02

Secure in position

The panels are secured on the bed before any concrete goes in, so it holds position as it fills.

03

Fill from the quayside

Concrete is pumped from the quay. Divers move the filling hose between filler points as the panel fills, each filling taking about 6 hours.

04

Work the quay in parallel

How many panels go in per day depends on how many working areas are open along the quay and how many dive teams are in use.

05

Trench and tie the edges

The apron edges are placed in a trench with the hinged edge block detail tied into the main slab.

FIG. 3 One panel, from yard to bed. Laid out and checked, rolled onto its lifting tube, then lowered over the quay edge and unrolled on the dredged bed before any concrete is pumped. 1 of 3.
FIG. 4 Filling from the quay. A truck-mounted boom pump reaches the panel from the quayside, and divers move the hose between the filler points as it fills.
FIG. 5 The whole spread. Boom pump and ready-mix truck set up on the quay, which is where the concrete for every panel is pumped from.

The apron edge

For long-term protection it is vital that the concrete apron is not undermined at its edges. The edges are placed in a trench, which includes a hinged edge block detail.

These hinged edge blocks are tied into the main concrete apron, weigh 4 t each, and are designed to drop independently. That gives the apron additional protection against scour before any maintenance is needed, and the blocks are heavy enough to resist being flipped by trapped flow pressure.

Quay Wall Edge Detail Test 021
FIG. 6 The hinged edge detail under test. Each 4 t block is tied into the apron and drops independently as the bed beyond the trench moves.

Outcome

The berth carries 11,000 m² of sealed apron, taking the quay from −10.6 m to −12.5 m so larger vessels can dock, without compromising the stability of the quay wall. Because the layer is sealed and interlocking rather than deadweight, the protection is thin, and the depth stays in the water. The same principle applies wherever berth scour protection has to fit inside a fixed dredge box.

For long-term protection it is vital that the apron is not undermined at its edges, which is what the trench and the hinged edge blocks are there to prevent.

Also available
Credits

Who did what on this project

Client
Port of Szczecin

Owner of the quay and the berth deepening programme.

Contractor
Aarsleff

Carried out the installation of the concrete mattress scour protection.

Scour protection engineering
Proserve

Concrete mattress system, panel design and the hinged edge detail at the apron perimeter.

Where next

Continue

THE TECHNOLOGY

Concrete mattress

How the form is filled, the variants, and why a sealed interlocking layer needs no deadweight to resist propeller flow.

Read →
YOUR STRUCTURE

Quay walls

Szczecin is a block wall taken deeper. This is the same problem set out generally: protecting the bed at the toe of an existing wall.

Read →
Work with our engineers

Deepening a berth against an existing wall? Send us the as-built section and target depth.

Send us the as-built section of the wall and its toe, the depth you need and the vessel classes, and we will come back with an outline approach: apron thickness, extent and edge detail, and how much depth the wall can give up. If the wall cannot take it, we will say so.

What to send
No cost, and no obligation to proceed.