719 Grout Bags Under the Flood Barrier Caissons, MOSE, Venice, Italy

Venice’s flood gates only hold if the caissons housing them sit level, and each caisson weighs around 20,000 tonnes. They had to be bedded onto a dredged seabed undulating by up to 900 mm, under tidal flow constraints, with limited diver access, and the works were not reversible. Manual levelling and conventional concrete infill were both ruled out.

Mose Barrier
Project data

Location

Malamocco & Lido San Nicolò inlets, Venice

Client

Grandi Lavori Fincosit

Designer

Technital

System

Grout Bag Foundation System

Period

2012 – 2014

Results at a glance

719 bags

Grout bags fully filled

Across both the Malamocco and Lido San Nicolò inlets

900 mm

Seabed undulation absorbed

Local variation taken up by the bag, with no prior levelling

20,000 T

Per caisson supported

Units up to 60 m long and 48 m wide, held to gate tolerance

Contents

In brief

The constraints

MOSE is the flood defence protecting Venice and its lagoon from tidal surge. The city has long suffered acqua alta: the 1966 flood reached 194 cm above mean sea level, and by the early 2000s tides over 110 cm were occurring more than 60 times a year.

It closes the lagoon’s three inlets with mobile steel flap gates housed in precast concrete caissons, each up to 60 m long, 48 m wide and around 20,000 tonnes.

The gates only hold if the caissons housing them sit level. Each had to be bedded onto a dredged seabed undulating by up to 900 mm, under tidal flow constraints, with limited diver access, and the works were not reversible. Manual levelling and conventional concrete infill were both ruled out.

FIG. 1 The MOSE gates raised. Mobile steel flap gates, housed within the precast caissons placed across the lagoon's inlets, close the inlet against tidal surge.

Proserve’s remote grouted fabric formwork was selected against four requirements. Table 1 sets out each, and what the system does to meet it.

Table 1 · Requirement and how the system meets it
CAPABILITY
CONDITION
WHAT IT DOES
Conforms to the
bed as found
Local undulations
of up to 900 mm
The bag expands to fill the gap it meets, so the trench needed no manual levelling before the caisson arrived.
High-friction
contact
Tailored grout infill
Uniform, high-friction contact across the base of the caisson, provided through tailored grout infill.
Surface-operated
grouting
No diver
involvement
Pumps and controls sit on the barge. Diver access at these depths and tidal flows was limited, and the works were not reversible.
Vent-controlled
filling
Embedded
sensors, real-time
Vent pipes carry sensors that confirm grout rise and pressure as the fill proceeds, and trigger shut-off at full contact.

Together those give a low-risk, high-control foundation method suitable for large-scale marine structures, with the filling both operated and monitored from the surface.

The solution

The grout bag units were fabricated from grout-tight, permeable woven fabric, pre-fixed beneath each caisson and protected within PVC sleeves. Internally compartmentalised, the system allowed controlled expansion and conformance to the seabed.

Each unit was equipped with prefixed filler sleeves and upstanding vent pipes containing embedded sensors, so surface teams could monitor grout rise and pressure throughout the fill.

Full-scale development trials were carried out by the parties in 2009: bag expansion under pressure in simulated trench conditions, grout delivery verification with a neat cement mix, and CFD modelling of tow and launch forces to guide the restraint design. Fig. 2 is one of those test fillings.

FIG. 1 Cross section. A 200 mm apron takes the berth from −10.6 m to −12.5 m, closing with a 560 mm hinged edge block set in a trench at the outer edge.
Unfilled Filled
FIG. 2 Full-scale grout bag test filling, one of the 2009 development trials. The same bag before and after grouting: flat fabric on the left, expanded under pressure on the right. Drag the handle to compare.
FIG. 3 Grout bag fitted in its casing, hard into the recess. Prefixed filler sleeves and upstanding vent pipes, the vents carrying the embedded sensors that report grout rise and pressure to the surface. 1 of 3.

Constructability and installation

The preparation was done in the dry. The bags, their prefixed filler sleeves and their vent pipes were fitted beneath each caisson at the Malamocco yard, held hard into their recesses and protected within PVC sleeves. The grouting itself then ran fully from the surface, which is what eliminated diver involvement.

01

Cast and fit at the yard

Caissons were cast at the Malamocco yard and the grout bags fitted beneath each base, held hard into their recesses and protected within PVC sleeves.

02

Launch and tow

Each unit was launched using a ship lift and towed out to the inlet. CFD modelling of tow and launch forces had guided the restraint design.

03

Position on the trench bed

The caisson was placed within its pre-prepared trench bed and held on temporary jacks while the base was grouted.

04

Grout each compartment

Surface-mounted pumps delivered neat cement grout into each compartment in a controlled sequence, filling the internally compartmentalised bag progressively.

05

Confirm and shut off

Vent sensors triggered shut-off once full contact was confirmed. A typical caisson was filled over a two-day period, with no diver intervention at any stage.

FIG. 4 Fitting the bags in the dry. The bag units, filler sleeves and vent pipes were pre-fixed beneath the caisson at the yard, held hard into their recesses and protected within PVC sleeves.
FIG. 5 Filling from a floating barge. Pumps, grout supply and the vent monitoring all sit on the surface, which is what removes the dive team from the operation. 1 of 2.

The design of the fill allowed uplift to be controlled and washout to be avoided, and assured full base contact across complex seabed profiles. A typical caisson was filled over a two-day period, without diver intervention. Vent sensors triggered shut-off once full contact was confirmed.

FIG. 6 CGI of the grouted foundation. Not site photography: the filled bag beneath the caisson base, with the fill and vent lines running up the caisson face.

Outcome

The system performed reliably across all installations at both the Malamocco and Lido San Nicolò inlets, with 719 grout bags fully filled. Full grout contact was achieved beneath each caisson, and vent feedback confirmed uniform filling with no sign of overpressure or blowout. The foundations supported precise caisson placement and held the tight tolerances the gates need to stay in alignment.

Since the MOSE system was activated in 2020, Venice has remained protected during several high tide events that would historically have flooded much of the city. In November 2021 and again in December 2022, tides exceeded 130 cm but were fully held back.

  • Full surface-based installation, with no diver dependency
  • Foundation tolerances met across multiple large-scale units
  • Long-term structural stability established in difficult conditions
  • A continuing contribution to the protection of Venice from tidal flooding

The project reinforces the capability of Proserve’s automated fabric formwork to deliver repeatable, engineered foundation solutions in some of the world’s most sensitive marine environments.

Also available
Credits

Who did what on this project

Client and contractor
Grandi Lavori Fincosit

Delivered the caisson works at the Malamocco and Lido San Nicolò inlets.

Engineer
Technical

Named as engineer on the project.

Foundation system
Proserve

Grout bag foundation system, development trials and surface-operated grouting method.

Where next

Continue

THE TECHNOLOGY

Grout bags

The foundation grout bag system in general: fabric, compartments, vent control, and where surface-operated filling replaces diver work.

Read →
YOUR STRUCTURE

Caisson foundations

MOSE is a caisson set into a trench bed. This is the same problem set out generally: bedding a large precast unit onto an unlevel seabed to tolerance.

Read →
Work with our engineers

Bedding a heavy precast unit onto an unlevel seabed? Send us the unit and the bed survey.

Send us the unit size and base detail, the bed survey including undulation, and the tolerance you have to hold, and we will come back with an outline approach: compartment layout, fill and vent arrangement, and the filling sequence. If a conventional bedding layer is the better call, we will say so.

What to send
No cost, and no obligation to proceed.